Kitchen extension: the stages in order

Knowing the sequence helps you see where delays tend to start and which decisions need making when.

1. Design and approvals

Before anyone digs, the design is settled and the approvals are sorted. That might be permitted development, a planning application or a lawful development certificate, plus Building Regulations approval and, if a shared wall is involved, notices under the Party Wall etc. Act 1996. Structural calculations are usually prepared at this stage. This phase often takes longer than the building, and rushing it causes problems later.

2. Site set-up

The builder sets up access, protects the house, arranges the skip and often a temporary kitchen is set up inside. Services such as gas, water and electricity may need to be isolated or moved. If a drain runs where the extension is going, it needs to be dealt with early.

3. Groundworks and foundations

Trenches are dug for foundations, then inspected by building control before concrete goes in. On a sloping Folkestone plot the depth and form of the foundations can change once the ground is open, so ask how unexpected conditions are handled in the quote. Drainage is laid at this stage, and it is much harder to correct afterwards.

4. Walls and the opening

The new walls go up to the damp-proof course and then to full height. Meanwhile the old back wall is opened up. Steel beams are fitted with temporary support in place, which is the point when the house is at its most exposed. The structural work is normally inspected before it is covered.

5. Roof and weathertight

Roof structure, coverings, flashings and windows go on until the extension is closed to the weather. Only then can inside work proceed reliably. Delays in window or rooflight delivery can hold up this stage, so order early.

6. First fix

Electricians and plumbers run cables and pipes through walls and floors before plaster. This is the moment to decide where every socket, switch, light and radiator goes, because moving them later means cutting into finished walls. If you are choosing a kitchen, the layout should be final by now.

7. Insulation, plaster and screed

Insulation, plasterboard and plastering follow, and then floors. Wet trades need time to dry, and rushing paint onto damp plaster causes problems. Underfloor heating, if you are having it, goes in before the screed.

8. Second fix and the kitchen

Units, worktops, appliances, sockets, switches, light fittings and radiators go in. Worktops are often measured only after the units are in, which can add several days, and some materials have long lead times. Plan for that gap.

How long does each stage take?

We would rather not quote durations that depend on the house, the weather and the approvals. As a rule, the design and approvals stage is longer than most people expect, the build itself is measured in months and not weeks, and finishing takes longer than it looks from the outside. Ask for a written programme that shows the stages in order and says what each depends on, and expect it to move if the ground, the weather or deliveries change.

Drying times matter. Concrete, plaster and screed all need time before the next stage, and skipping it causes cracks and failed finishes later.

Decisions that cause the most delay

Windows and doors, because they have long lead times. The kitchen layout, because it fixes the electrics and plumbing. Tiles and flooring, because they affect levels. Make those three choices early, and the rest of the job tends to follow smoothly.

Who does what on site

A kitchen extension involves several trades in turn: groundworkers, bricklayers, carpenters, roofers, electricians, plumbers, plasterers, a kitchen fitter and decorators. A builder who manages them well keeps each one working in the right order, so no one is waiting. Ask who is on site each day, who is in charge when you are not there, and how you will be told when the plan changes. The answers tell you a lot about how the job will run.

9. Decoration, inspection and handover

Painting, flooring and final connections complete the job, followed by the building control final inspection and the completion certificate, which is worth keeping safe because a buyer's solicitor will ask for it later. Go through the work carefully before the final payment.

Related pages

Free site visit and quote

Tell us about the project at hello@folkestonebuilder.co.uk or on WhatsApp. We'll arrange a site visit to give you a proper quote.

Got a Folkestone project in mind? Start with a look at the site.

Free, no-obligation site visit and quote. Describe the job, send a few photos of the house or the space, and we will arrange a time to see it properly.