Snagging: checking the finished job

Almost every building project has small faults at the end. Snagging is the structured way of finding them while the builder is still on site.

What snagging means

A snag is a small defect or unfinished item: a paint miss, a sticking door, a gap in the sealant, a socket that is not level. They are normal. What matters is that they are listed, agreed and fixed rather than discovered gradually over the next year.

Do it in good light

Walk through in daylight, ideally in the morning, with the curtains open. Then go round again with the lights on. Many paint and plaster flaws only show in raking light. Take your time, and do not let the day of handover be rushed.

What to check

Look at walls and ceilings for cracks, dents and patchy paint. Open and close every door and window, and check that they latch and lock. Run every tap and flush every toilet, then check underneath for leaks. Test sockets with a plug-in tester or with a lamp, and try each switch and light. Look at tiling for even lines and clean grout. Check flooring for gaps and lifting edges. Try the heating in each room. Inspect the outside as well: render, brickwork, guttering, paving and anywhere the old and new meet.

Record it properly

Make a written list, room by room, with photographs of anything unclear. Date it, send a copy to the builder and keep one yourself. A vague comment that the bathroom needs finishing is hard to act on; a list that says grout missing behind the basin and door rubbing on the frame is easy to tick off.

Agree a date for fixing

Ask for a date by which the snags will be completed and put it in writing. Fair builders agree this without fuss. A short second visit to go through the list together saves arguments later.

Hold something back until it is done

It is common to agree in the contract that a small final payment is made once the snags are completed. If you want that arrangement, it has to be agreed in advance, not invented at the end. Check what your contract says about stage payments and the final balance.

Paperwork you should receive

For structural work, a Building Regulations completion certificate from the council or an approved inspector. For new electrical work, the electrical certificate. For gas or heating work, the relevant safety certificate. Also manuals and warranty details for appliances and fittings. Keep them all together, because you will be asked for them if you sell.

Problems that appear later

Some issues only show after the building has settled, dried out or gone through a season: hairline cracks in new plaster, shrinkage gaps at joints, doors that swell in damp weather. Ask the builder what is normal and how to report anything that is not. Do it promptly and in writing.

Snagging as the work goes along

The best snagging does not wait until the end. Walk through at the end of each stage, such as after first fix and after plastering, and look at what has been done while it is still easy to correct. Problems found before the walls are closed or the tiles are fixed cost very little to put right. After the finish, they can mean taking out work that has been done.

Photographs at each stage also help. A picture of pipework and cables before plaster is a good record of where they are, which is useful if you want to hang something later.

Small things that matter

Check that the paint matches in colour and sheen across a wall, that door handles line up, that skirting boards meet neatly in corners, and that the sealant around baths and basins is continuous. Look under the sink, behind the toilet and at the underside of the stairs. A neat finish is a sign of care throughout.

If you cannot agree

Stay calm, keep communications in writing and refer to the quote and the agreed specification. If a dispute cannot be settled between you, the contract and independent advice are the next step. Most disagreements are resolved by a clear list and a reasonable conversation.

Related pages

Free site visit and quote

Tell us about the project at hello@folkestonebuilder.co.uk or on WhatsApp. We'll arrange a site visit to give you a proper quote.

Got a Folkestone project in mind? Start with a look at the site.

Free, no-obligation site visit and quote. Describe the job, send a few photos of the house or the space, and we will arrange a time to see it properly.